Numerous Interstate rehabilitation projects loom in Northern Kentucky

Local and out-of-state travelers advised to be aware, prepared

I-275 in Boone County and I-71 in Boone and Gallatin Counties are underway

 

COVINGTON, Ky. – The Kentucky Transportation Cabinet District 6 Office is preparing to coordinate several pavement rehabilitation projects on Interstates 71, 75, 275, and 471 in Northern Kentucky.

 “While the rehabilitations of our interstates will benefit motorists and improve roadway pavement conditions, the projects will cause congestion and back ups,” said Rob Hans, District 6 chief engineer. “We are getting the word out now to prepare local commuters and travelers so that they can plan accordingly.”

Median cable barriers are now being installed on eastbound I-275 in Boone County.  Completion is expected near the end of November.

A $35.8 million asphalt overlay roadway rehabilitation project on northbound and southbound I-71 has begun.  The 18-mile section goes from the I-71/I-75 interchange to the vicinity of the Sparta Exit 57 (77.7 – 59.7 mile marker).   The rehab project will include addressing base failures (potholes and ruts), repairing three slide areas and installing guardrail at various locations.  Message boards will warn motorists of the work zone and lane closures.  The speed limit will be reduced to 55 mph. 

Crews began preliminary work Nov. 7 and will continue working as weather allows.  There will be no work during the 2010 holidays.  The project will be complete by Nov. 30, 2011. 

Eaton Asphalt Paving Co. Inc., of Covington, was awarded the low-bid contract.

 

Another project is a $2.9 million concrete pavement repair on westbound I-275 in Boone County.  Sections of pavement will be replaced between the Kenton County line/Turfway Road underpass and the airport interchange, which is Exit 4. Message boards will warn motorists of the work zone and lane closures.  The speed limit will be reduced to 55 mph during the construction and a double fine zone will be in enforced when workers are present and signs are posted.

Double lane closures will occur on weekends.  The project will begin in November and continue until Christmas.  There will be no work during the Thanksgiving holiday weekend.  The project will resume in spring 2011 and will be complete by June. 

W.L. Harper Co., of Hebron, Kentucky, was awarded the low-bid contract.

 

Other interstate repair projects also will affect motorists’ routines.  Commuters should consider other options, such as carpooling or public transit. 

Most work will take place nights and weekends to avoid peak traffic hours, but there will still be lane closures.  “We are looking at every option so we can coordinate these projects to do the least amount of disruption,” Hans said.

Projects include:

  • I-275 median cable barriers in Boone County totaling 12.1 miles – $1.3 million.  Work already in progress.
  • I-275 concrete pavement repairs.

-      Boone County, mentioned above, beginning Nov. 1, 2010 - $2.9 million.   Expected completion June 15, 2011.  Work already in progress.

-      Kenton County from US 25 to KY 9 – TBA November 2010.

-      Campbell County from KY 9 to the Ohio River – TBA spring 2011.

  • I-71 NB and SB will have structural asphalt overlays placed from the I-75 interchange to the six-lane section before the Sparta Exit 57 totaling 18 miles – mentioned above, began Nov. 7, 2010 - $35.8 million.   Work completed by November 30, 2011.  Work already in progress.
  • I-75 NB and SB will be resurfaced from the Turfway Exit 182 to the I-71 interchange, approximately 10 miles – TBA.
  • I-75 NB and SB will have pavement rehabilitation from the Brent Spence Bridge to Rivard Drive underpass, totaling 3 miles - TBA.
  • I-275 median cable barriers in Kenton and Campbell counties, approximately 11 miles – TBA.
  • Painting of all I-275 steel bridges in Kenton County, including the Dr. Poweleit Licking River Bridge, KY 16, KY 17, KY 1303, US 25, CNO and TP Railroad Bridge, Crescent Springs Road and I-75/I-275 interchange bridges - TBA.
  • I-471 concrete pavement repairs – currently scheduled for 2012.

Times and locations of projects will vary, with most beginning in spring 2011.  Disruption of traffic flow will be unavoidable.  There are no “off hours” when it comes to road construction.  To avoid interstate construction, motorists are encouraged to seek alternate routes.  Motorists who must travel the interstates should be prepared for long delays. 

Federal funds for interstate maintenance are being used for the projects. 

 

##